Track-laying completed on 75 percent of Qinghai-Tibet Railway
(Xinhua)
Updated: 2005-04-26 18:37

Track-laying has been completed on 852 kilometers, or 75 percent of the 1,142-kilometer Qinghai-Tibet Railway, the first railway linking Tibet with the rest of China, according to the headquarters for constructing the project.

 This year will see track laid at an elevation of 5,070 meters, the highest railway spot in the world, said La Youyu, a deputy director with the construction headquarters, Tuesday.

The railway will be finished by the end of this year and put into trial operation by July 1, 2006.

 The full length of the Qinghai-Tibet Railway, between Xining, the capital of Qinghai Province, and Lhasa, the capital of Tibet Autonomous Region, will be 2,040 kilometers.

Construction of the first phase of the railway, between Xining and Golmud, Qinghai, began in 1958 and ended in 1984. In 2001, the 1,142-kilometer-long second phase, from Golmud to Lhasa, was launched.

Track-laying has proceeded smoothly on the railway, which crawls on the snow-covered Qinghai-Tibet Plateau, often called the "roof of the world." Railway builders have made efforts to protect the environment and deal with other problems such as frozen earth and the prevention of highland disorder and epidemics to build the railway.



 
  Today's Top News     Top China News
 

KMT leader arrives in Nanjing for historic visit

 

   
 

China: EU textile move could harm trade ties

 

   
 

Families grieve, 73 dead in Japan train crash

 

   
 

Yen rallies, bet is on China revaluation

 

   
 

Economic growth expected to slow down

 

   
 

Olympic venues to be opened for public use

 

   
  KMT chairman leaves Taipei for mainland visit
   
  Olympic venues to be opened for public use
   
  Invented something? Now flaunt it here
   
  Niujie Mosque in Beijing gets facelift
   
  Country improves river's navigation
   
  Police sorry for slur on Henan 'criminals'
   
 
  Go to Another Section  
 
 
  Story Tools  
   
  Related Stories  
   
Ministry releases plan for rail construction
   
Postal, rail sectors open to private firms
   
Beijing-Tianjin commuter rail to start construction
   
Beijing-Tianjin commuter rail to start construction
   
Railway chief steams ahead with reforms
   
Ministry of Railways streamlines administration
   
Lanzhou-Chongqing railway to be constructed next year
  News Talk  
  It is time to prepare for Beijing - 2008  
Advertisement
         
主站蜘蛛池模板: 阿克苏市| 东乡县| 安吉县| 双城市| 黎平县| 嫩江县| 汶川县| 宁阳县| 内丘县| 麻栗坡县| 宜春市| 庆城县| 香河县| 朔州市| 宜都市| 米泉市| 随州市| 苗栗市| 鸡泽县| 江源县| 武义县| 虹口区| 小金县| 沁阳市| 双辽市| 锦州市| 长乐市| 包头市| 洮南市| 兴海县| 云南省| 南开区| 临城县| 新和县| 吐鲁番市| 合江县| 蒲城县| 田东县| 临武县| 隆尧县| 京山县|