Africa Focus China's CREC to complete section of Ethiopia's key railway project

Xinhua | Updated: 2015-05-19 20:40

ADDIS ABABA - The Sebeta/Addis Ababa-Adama- Mieso railway, which is a section of Ethiopia's key railway project of the Addis Ababa-Djibouti railway being built by the China Railway Group (CREC) is nearing completion.

As the track-laying activity is approaching to completion, a grand ceremony was held on Monday in Adama town about 99 km south of Ethiopia's capital Addis Ababa, where senior government officials, diplomats, Chinese and local staff of CREC as well as residents of Adama town celebrated the landmark chapter of the project.

The Sebeta/Addis Ababa-Mieso railway project covers a total length of 329.145 km. The Ababa-Adama section is a double track with 115 km length while the Adama-Mieso is a single track covering 214.145 km.

The standard-gauge railway, which is one section of the first Ethiopia's national railway network, has been contracted by CREC with a total cost of nearly two billion US dollars.

With the designed speed of 120km/h, the electrified-railway connects Addis Ababa with important cities of Adama, Dire Dawa, and Djibouti Port, and is the main transporting corridor for imports and exports of Ethiopia and the inland of East Africa.

Stating that the project is the first modern railway in Ethiopia, Prime Minister Hailemariam Desalegn said the project is a blood-line of the country's economy.

"In addition to its contribution to facilitation of transportation in the country, the project plays significant role in sharing experience and transfer of technology and skills from the Chinese to Ethiopians, which in the future will enable Ethiopian professionals carry out such infrastructure projects in the country on their own," he said.

Stating that more than 80 percent of the project has been completed so far, Getachew Betru, CEO of the Ethiopian Railway Corporation (ERC), noted that the speed and works on the construction of the project show that it would be fully completed as per the contract schedule and standard.

Getachew called on all concerned parties and the local community to continue to display the usual collaboration and provide support to the undertaking of the project towards its successful completion, and then test-ride and handover ceremony.

Previous 1 2 Next

Most Viewed in 24 Hours
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
主站蜘蛛池模板: 南和县| 富川| 安西县| 武清区| 邵阳县| 南木林县| 威海市| 宁乡县| 巩留县| 隆德县| 花莲市| 调兵山市| 沈丘县| 汨罗市| 会昌县| 壤塘县| 宣武区| 廊坊市| 深圳市| 河北区| 黄骅市| 原阳县| 乳山市| 满洲里市| 类乌齐县| 泽普县| 巴青县| 称多县| 石棉县| 甘洛县| 永丰县| 阿拉尔市| 新密市| 兴和县| 阿合奇县| 色达县| 晋中市| 门头沟区| 田东县| 玉山县| 宝山区|